Project
|
Ultimate client
|
Length of time
|
Images
|
|
|
|
|
|
|
|
Mechanical upgrading work on 3 open-cast mining handling systems
|
Dunbar, SCOTLAND
|
48 weeks
|
Click here |
|
|
|
|
|
|
|
Mechanical erection of a 90/32 ton slab handling crane
|
Dillinger Hüttenwerke in Dillingen Saar
|
8 weeks
|
Click here |
|
|
|
|
|
|
|
Mechanical and electrical installation of 2 PTM cranes (for aluminium smelting furnaces)
|
|
12 weeks
|
Click here |
|
|
|
|
|
|
Mechanical and electrical installation of pneumatic ship unloader
|
Elkem, MosjØen/Norway
|
11 weeks
|
Click here |
|
|
|
|
|
|
Dismantling (following accident) and erection of pneumatic ship unloader
|
Aluminium Dunkerque, Dunkirk/France
|
22 weeks
|
Click here |
|
|
|
|
|
|
All-in final mechanical and electrical installation up to serviceability of three of the currently largest container bridges in the world
|
Maersk, Algeciras/Spain
|
39 weeks
|
Click here |
|
|
All-in electrical installation for 2 coil handling cranes
|
Thyssen, Krefeld
|
5 weeks
|
-
|
|
|
|
|
|
|
|
Electrical installation for slag container crane
|
|
29 weeks
|
-
|
|
|
|
|
|
|
Electrical installation for 2 refuse cranes
|
AVA, Augsburg
|
6 weeks
|
-
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|