Project
|
Ultimate customer
|
Length of time
|
Images
|
|
|
|
|
|
|
|
Realisation of a colouring facility for corrugated slabs, re-arrangement of the building elements and fitting new elements
|
Leimen, GERMANY
|
6 weeks
|
Click here |
|
|
|
|
|
|
|
Mechanical installation of a circulating lifter, model erection of a circulating conveyor, model erection of a sorting and repacking unit and model oval for equipment testing.
|
St. Ingbert, GERMANY
|
6 weeks
|
Click here |
|
|
|
|
|
|
|
Mech. and electrical installation of a solar module production unit
|
Landsberg, GERMANY
|
5 weeks
|
Click here |
|
|
|
|
|
|
|
Replacing flight conveyor for cleaning plant
|
Dingolfing, GERMANY
|
2 weeks
|
Click here |
|
|
|
|
|
|
|
Mechanical installation of a platform and conveyor belts XB 295
|
Neuss, GERMANY
|
4 weeks
|
Click here |
|
|
|
|
|
|
|
Mechanical/electrical installation of a robot line
|
Freiberg, GERMANY
|
12 weeks
|
- |
|
|
|
|
|
|
|
All-in erection for the test set-up of a circulating lifter with individual work sections
|
Atria Tekniikka Oy Finnland in Nurmo Laquantie/Finland
|
4 weeks
|
Click here |
|
|
|
|
|
|
|
Mechanical erection of a meat-sorting system of the conveyor technique in the existing plant and in a completely new plant
|
Atria Tekniikka Oy Finnland in Nurmo Laquantie/Finland
|
24 weeks
|
Click here |
|
|
|
|
|
|
Mechanical and electrical installation of loading gantries in bumper production for loading and unloading a shelf system
|
REHAU, Feuchtwangen
|
6 weeks
|
Click here |
|
|
|
|
|
|
Mechanical and electrical installation of the materials handling equipment in a shelf system for bumpers
|
REHAU, Feuchtwangen
|
7 weeks
|
Click here |
|
|
|
|
|
|
Mechanical and electrical installation of a crankshaft line
|
BMW AG, Munich
|
34 weeks
|
Click here |
|
|
|
|
|
|
|
Mechanical and electrical installation of a crankshaft production line M-273 / OM 642
|
Daimler Chrysler AG, Untertürkheim
|
34 weeks
|
|
|
|
|
|
|
|
|
Mechanical and electrical installation of a crankshaft production line M-272
|
Daimler Chrysler AG, Untertürkheim
|
33 weeks
|
|
|
|
|
|
|
|
Mechanical and electrical installation of a camshaft production line
|
Ford, Valencia/Spain
|
28 weeks
|
Click here |
|
|
|
|
|
|
Mechanical and electrical installation of a crankshaft production line
|
Ford, Valencia/Spain
|
7 weeks
|
Click here |
|
|
|
|
|
|
Mechanical, electrical and pneumatic installation of a materials handling system
|
VW AG Cordoba/Argentina
|
24 weeks
|
|
|
|
|
|
|
|
|
Installing automatic stations in the engine assembly line
|
Daimler Chrysler AG, Mannheim
|
4 weeks
|
-
|
|
|
|
|
|
|
|
Final assembly crankshaft interlinking system
|
General Motors, San Jose dos Campos/Brazil
|
21 weeks
|
-
|
|
|
|
|
|
|
Final assembly flexible production line
|
General Motors HEC, Port Melbourne/Australia
|
23 weeks
|
|
|
|
|
|
|
|
Final assembly flexible production line 13 loading gantries Line 2
|
Opel AG, Szentgotthard/Hungary
|
32 weeks
|
-
|
|
|
|
|
|
|
Upgrading and overhaul of crankshaft production line, 25 loading gantries und 250 metre run of belt interlinking
|
BMW AG, Steyr/Austria
|
9 weeks
|
-
|
|
|
|
|
|