References - Equipment Engineering
Project
Ultimate client
Length of time
Images
All-in electrical installation of ship unloaders, handling technology, large-scale silo plant in the Qatalum aluminium works
Doha, QATAR
52 weeks
Click here
Mechanical and electrical installation of a HWS moulding machine for foundries
Chemnitz, GERMANY
7 weeks
Click here
Mechanical installation of silo and mixing technology in a large bakery
Bergkirchen, GERMANY
16 weeks
Click here
Mechanical installation of an air-freight distribution centre
Doha, QATAR
58 weeks
Click here
Installation of a Fluidcon handling system in a cement works
Dotternhausen, GERMANY
30 weeks
Click here
Installation of a plant for the cold crushing of dry lignite
Spremberg - Schwarze Pumpe, GERMANY
58 weeks
Click here
Mechanical and electrical dismantling and re-installation of a flat glass cutting line
Springs-Gauteng, SOUTH AFRICA
19 weeks
Click here
Installation of a complete gypsum plaster factory incl. gypsum calcination and gypsum plasterboard facility
Oosterhout, NETHERLANDS
35 weeks
Click here
Mechanical installation of a batch and cullet recycling plant
Boffzen, GERMANY
23 weeks
Click here
Mechanical installation of a batch and cullet recycling plant
Moscow, RUSSIA
51 weeks
Click here
Mechanical and electrical installation of a ring hearth furnace
Rastatt, GERMANY
10 weeks
Click here
Mech. and electr. dismantling and installation of a moulding sand preparation plant at AGVS in Villingen-Schwenningen
Villingen-Schwenningen, GERMANY
3 weeks
Click here
Mechanical and pneumatic installation of a handling system at PCW in Eilenburg
Eilenburg, GERMANY
3 weeks
Click here
Mechanical and electrical installation of a billet grinder in a steelworks
Neunkirchen, GERMANY
9 weeks
Click here
Mechanical overhaul and installation of a batch conditioning plant and cullet recycler of a flat glass factory
Hombourg, FRANCE
18 weeks
Click here
Mechanical and electrical installation of a flat glass cutting plant
Dabrowa Gornicza, POLAND
9 weeks
-
Mechanical and electrical installation of a sand preparation plant for a foundry
Bayreuth, GERMANY
7 weeks
Click here
Mechanical installation of a tobacco preparation plant
Junan, TAIWAN
36 weeks
Click here
Mechanical installation of a synthetic granulate handling system
Tewkesbury , UK
24 weeks
Click here
Mechanical upgrading of a kiln heating system
Pfungstadt, GERMANY
12 weeks
Click here
Mechanical installation of a batch plant with batch handling and cullet recycling
Springs, SOUTH AFRICA
20 weeks
Click here
Mechanical and electrical installation of 7 furnaces
Copenhagen, DENMARK
13 weeks
Click here
Mechanical installation of a high-rise rack store
Baruth, GERMANY
20 weeks
Click here
Mechanical installation of a biomass heat/power station in Rotterdam- Botlek/Holland
Rotterdam, NETHERLANDS
40 weeks
Click here
Steelwork and mechanical installation of a gypsum plasterboard production line with dryer
Escusar, SPAIN
60 weeks
Click here
High-rise rack store, Kerpen
Boll & Kirch Filterbau GmbH, Kerpen
10 weeks
Click here

High-rise rack store, Moscow

Trio Invest Ltd., Domodedovo

18 weeks
Click here
Mechanical re-erection of a wood crusher and sorting plant
PEG Peine Entsorgungsgesellschaft in Hohenhammeln/Peine
10 weeks
Click here
Mechanical installation of a glass batch plant, CAUSTIC-SODA plant, refuse glass return and air-conveying lines
Guardian Industries, Czestochowa/Poland
25 weeks
Click here
Mechanical installation of a glass batch plant and glass refuse recycling
Manfredonia Vetro, Manfredonia/Italy
35 weeks
Click here
Mechanical installation of a glass batch plant and adaptation to existing glass batch discharging conveyor belt
Glaverbel, Moustier/Belgium
22 weeks
Click here
Mechanical installation of machinery, supporting steelwork, all-in electrical installation and optimization of the machines (prototype) of a residual refuse recycling plant
AMAV, Fusina/Italy
33 weeks
Click here

Mechanical erection of a batch plant

Rayen Cura, Mendoza/Argentina

17 weeks
Click here
Complete installation of a high-rise rack store
Roto Frank AG, Leinfelden
19 weeks
-
Mechanical upgrading and overhaul of a batch plant for window glass
Rebuild Luxgard II, Dudelange/Luxembourg
14 weeks
-