Project
|
Ultimate client
|
Length of time
|
Images
|
|
|
|
|
|
|
|
All-in electrical installation of ship unloaders, handling technology, large-scale silo plant in the Qatalum aluminium works
|
Doha, QATAR
|
52 weeks
|
Click here |
|
|
|
|
|
|
|
Mechanical and electrical installation of a HWS moulding machine for foundries
|
Chemnitz, GERMANY
|
7 weeks
|
Click here |
|
|
|
|
|
|
|
Mechanical installation of silo and mixing technology in a large bakery
|
Bergkirchen, GERMANY
|
16 weeks
|
Click here |
|
|
|
|
|
|
|
Mechanical installation of an air-freight distribution centre
|
Doha, QATAR
|
58 weeks
|
Click here |
|
|
|
|
|
|
|
Installation of a Fluidcon handling system in a cement works
|
Dotternhausen, GERMANY
|
30 weeks
|
Click here |
|
|
|
|
|
|
|
Installation of a plant for the cold crushing of dry lignite
|
Spremberg - Schwarze Pumpe, GERMANY
|
58 weeks
|
Click here |
|
|
|
|
|
|
|
Mechanical and electrical dismantling and re-installation of a flat glass cutting line
|
Springs-Gauteng, SOUTH AFRICA
|
19 weeks
|
Click here |
|
|
|
|
|
|
|
Installation of a complete gypsum plaster factory incl. gypsum calcination and gypsum plasterboard facility
|
Oosterhout, NETHERLANDS
|
35 weeks
|
Click here |
|
|
|
|
|
|
|
Mechanical installation of a batch and cullet recycling plant
|
Boffzen, GERMANY
|
23 weeks
|
Click here |
|
|
|
|
|
|
|
Mechanical installation of a batch and cullet recycling plant
|
Moscow, RUSSIA
|
51 weeks
|
Click here |
|
|
|
|
|
|
|
Mechanical and electrical installation of a ring hearth furnace
|
Rastatt, GERMANY
|
10 weeks
|
Click here |
|
|
|
|
|
|
|
Mech. and electr. dismantling and installation of a moulding sand preparation plant at AGVS in Villingen-Schwenningen
|
Villingen-Schwenningen, GERMANY
|
3 weeks
|
Click here |
|
|
|
|
|
|
|
Mechanical and pneumatic installation of a handling system at PCW in Eilenburg
|
Eilenburg, GERMANY
|
3 weeks
|
Click here |
|
|
|
|
|
|
|
Mechanical and electrical installation of a billet grinder in a steelworks
|
Neunkirchen, GERMANY
|
9 weeks
|
Click here |
|
|
|
|
|
|
|
Mechanical overhaul and installation of a batch conditioning plant and cullet recycler of a flat glass factory
|
Hombourg, FRANCE
|
18 weeks
|
Click here |
|
|
|
|
|
|
|
Mechanical and electrical installation of a flat glass cutting plant
|
Dabrowa Gornicza, POLAND
|
9 weeks
|
- |
|
|
|
|
|
|
|
Mechanical and electrical installation of a sand preparation plant for a foundry
|
Bayreuth, GERMANY
|
7 weeks
|
Click here |
|
|
|
|
|
|
|
Mechanical installation of a tobacco preparation plant
|
Junan, TAIWAN
|
36 weeks
|
Click here |
|
|
|
|
|
|
|
Mechanical installation of a synthetic granulate handling system
|
Tewkesbury , UK
|
24 weeks
|
Click here |
|
|
|
|
|
|
|
Mechanical upgrading of a kiln heating system
|
Pfungstadt, GERMANY
|
12 weeks
|
Click here |
|
|
|
|
|
|
|
Mechanical installation of a batch plant with batch handling and cullet recycling
|
Springs, SOUTH AFRICA
|
20 weeks
|
Click here |
|
|
|
|
|
|
|
Mechanical and electrical installation of 7 furnaces
|
Copenhagen, DENMARK
|
13 weeks
|
Click here |
|
|
|
|
|
|
|
Mechanical installation of a high-rise rack store
|
Baruth, GERMANY
|
20 weeks
|
Click here |
|
|
|
|
|
|
|
Mechanical installation of a biomass heat/power station in Rotterdam- Botlek/Holland
|
Rotterdam, NETHERLANDS
|
40 weeks
|
Click here |
|
|
|
|
|
|
|
Steelwork and mechanical installation of a gypsum plasterboard production line with dryer
|
Escusar, SPAIN
|
60 weeks
|
Click here |
|
|
|
|
|
|
|
High-rise rack store, Kerpen
|
Boll & Kirch Filterbau GmbH, Kerpen
|
10 weeks
|
Click here |
|
|
|
|
|
|
|
High-rise rack store, Moscow
|
Trio Invest Ltd., Domodedovo
|
18 weeks
|
Click here |
|
|
|
|
|
|
Mechanical re-erection of a wood crusher and sorting plant
|
PEG Peine Entsorgungsgesellschaft in Hohenhammeln/Peine
|
10 weeks
|
Click here |
|
|
|
|
|
|
Mechanical installation of a glass batch plant, CAUSTIC-SODA plant, refuse glass return and air-conveying lines
|
Guardian Industries, Czestochowa/Poland
|
25 weeks
|
Click here |
|
|
|
|
|
|
Mechanical installation of a glass batch plant and glass refuse recycling
|
Manfredonia Vetro, Manfredonia/Italy
|
35 weeks
|
Click here |
|
|
|
|
|
|
Mechanical installation of a glass batch plant and adaptation to existing glass batch discharging conveyor belt
|
Glaverbel, Moustier/Belgium
|
22 weeks
|
Click here |
|
|
|
|
|
|
|
Mechanical installation of machinery, supporting steelwork, all-in electrical installation and optimization of the machines (prototype) of a residual refuse recycling plant
|
AMAV, Fusina/Italy
|
33 weeks
|
Click here |
|
|
|
|
|
|
|
Mechanical erection of a batch plant
|
Rayen Cura, Mendoza/Argentina
|
17 weeks
|
Click here |
|
|
|
|
|
|
Complete installation of a high-rise rack store
|
Roto Frank AG, Leinfelden
|
19 weeks
|
-
|
|
|
|
|
|
|
Mechanical upgrading and overhaul of a batch plant for window glass
|
Rebuild Luxgard II, Dudelange/Luxembourg
|
14 weeks
|
-
|
|
|
|
|
|